BMP ID |
Short Title |
Text of BMP |
---|
11200 |
Action plan if methane concentration increases |
"5.2 Water Well Monitoring. … If the methane concentration level increases by more than 5 mg/L between sampling periods, or increase to more than ... |
11199 |
Action plan if testing reveals thermogenic or intermediate mix |
"5.2 Water Well Monitoring. … If the carbon isotope test results in a thermogenic or intermediate mix signature . . .an action plan shall be ... |
11205 |
Additional post completion water tests |
"5.2 Water Well Monitoring. … Additional 'post completion' test(s) may be required if changes in water quality are identified during follow-up ... |
11166 |
Adoption of Road Impact Fee Program |
"3.3 Adoption of Road Impact Fee or Road Maintenance and Improvement Fee Program. The County is presently undertaking a feasibility study for the ... |
11198 |
Annual testing if testing reveals thermogenic or intermediate mix |
"5.2 Water Well Monitoring. . . . If the carbon isotope test results in a thermogenic or intermediate mix signature, annual testing shall be ... |
11808 |
Applicable federal regulations |
"4. Compliance with all applicable regulations of the BLM, BIA and the Southern Ute Indian Tribe when conducting operations on lands subject to such ... |
11237 |
Blow down shut-in well currently monitored by Chevron |
"7.4 On a well by well basis, and prior to producing wells for which a County Infill Permit has been obtained, and only to the extent not already ... |
11151 |
Calculating degree of noncomformity with setback requirements |
"2.4 Legal Non-Conforming Uses and Setbacks: … The increase, if any, in degree of nonconformity shall be the net difference between the two . . . ... |
11245 |
Calibrating reservoir simulation model |
"7.6 To the extent not already completed pursuant to Article VII 8 of the WAIC MOU, as sufficient data is collected, calibrate the 2008 reservoir ... |
11215 |
COGCC Approval of outcrop monitoring wells |
"7.1 . . .The Proposed locations of these wells will be discussed with and approved by the COGCC project manager for the La Plata County portion of ... |
11231 |
COGCC reviewing assessment and taking action |
"7.3 . . .The COGCC shall review the assessment and take appropriate action to pursue further investigation and remediation if warranted." |
11212 |
COGCC-ordered remediation if monitoring reveals a possible lack of zonal isolation |
"[6] . . .If the monitoring reveals a possible lack of zonal isolation, the COGCC may then conduct or order any necessary remediation ·or other ... |
11807 |
Compliance terms |
"2. Compliance with the terms and provisions of all of the Commission's health, safety, welfare and environmental rules and regulations now or ... |
11806 |
Compliance terms |
"1. Compliance with all terms, conditions and provisions of prior Commission Orders in Cause No. 112, including without limitation, the specific ... |
11178 |
Comply with weight restrictions |
"3.7 Produced Water Hauling. … In those instances where the utilization of a water hauling truck is required, Chevron agrees to strictly comply ... |
11196 |
Compositional analysis and carbon isotopic analyses |
"5.2 Water Well Monitoring. … If free gas or a methane concentration level greater than 2 mg/L is detected in a water quality testing well, ... |
11207 |
Copies of water test results provided |
"5.2 Water Well Monitoring. … Within three (3) months of collecting the samples used for the test, copies of all test results described above ... |
11155 |
County exercises good faith in performing road work from impact fees |
"3.1 Road Maintenance and Improvement Fees. County and Chevron have determined that specific land use activities by Chevron within the Infill ... |
11170 |
County provides notice of intended projects |
"3.4 Submission of Information: . . . The County agrees to reciprocate [Chevron provision of notice on travel routes and plans] and provide notice ... |
11156 |
County shall control road impact work |
"3.1 Road Maintenance and Improvement Fees: . . . The County shall control the sequencing and timing of such [road impact] work" |