University of Colorado at Boulder
BMP of Oil and Gas Development

Browse BMPs

You are viewing BMP records related to the Surface Operating Standards and Guidelines for Oil and Gas Exploration and Develoment (aka The Gold Book) publication.

BMP ID Short Title Text of BMP
474 50 percent of the pit should be below original ground level Well Sites: Reserve Pits: "If [locating the pit on the drill pad next to the high wall] is not possible, at least 50 percent of the reserve pit ...
507 Accommodate a 10-year flood with culverts Drainage and Drainage Structures: Surface Drainage: "Culverts should accommodate a 10-year flood without development of a static head and avoid ...
7929 All facility structures will be painted a color that blends with nature "All long-term facility structures, including worker housing, will be painted a color that enables the facilities to blendin with the natural ...
7919 All roads will be constructed to a safe standard "All new roads will be designed and constructed to a safe and appropriate standard, "no higher than necessary"to accommodate intended vehicular use."
7895 All topsoils will be removed and stockpiled for reuse "All surface soil materials (topsoil) are to be removed from the entire cut and fill area and temporarily stockpiled for reuse during interim and ...
506 Allow for debris passage Drainage and Drainage Structures: Surface Drainage: "The design may need to allow for debris passage, mud flows, and water heavily laden with silt, ...
490 Apply mulch or other sediment control measures Road Design and Construction: Construction and Reclamation Considerations: "To ensure the stability of freshly topsoiled slopes during revegetation, ...
7940 Areas not used will be reclaimed "Areas not used for production purposes will be reclaimed and blended into the surrounding terrain, reseeded, and erosion control measures installed."
7939 At producing wells, operators will reduce slopes "At producing wells, the operators will reduce slopes to original contours."
456 Avoid areas subject to erosion and soil movement Well Sites: Site Selection and Design: "Operations should also be avoided or properly mitigated in riparian areas, floodplains, playas, lakeshores, ...
471 Avoid constructing reserve pits in areas of shallow groundwater Well Sites: Reserve Pits: "Avoid constructing reserve pits in areas of shallow groundwater."
491 Avoid construction with saturated or frozen soils Road Design and Construction: Construction and Reclamation Considerations: "Construction with saturated or frozen soils results in unstable roads and ...
7908 Avoid construction within saturated/frozen soils "Construction within saturated or frozen soils should be avoided."
455 Avoid locations on steep slopes Well Sites: Site Selection and Design: "Well locations constructed on steep slopes cost more to construct, maintain, and reclaim and result in ...
7893 Avoid operations in riparian areas, floodplains, and wetlands "Operations should be avoided or properly mitigated in riparian areas, floodplains, wetlands, and areas subject tosevere erosion and mass soil ...
519 Avoid steep hillsides and water courses Pipelines and Flowlines: Construction: "Steep hillsides and water courses should be avoided in the location of pipelines and flowlines."
516 Avoid wetlands if possible Drainage and Drainage Structures: Wetland Crossings: "Wetlands are especially sensitive areas and should be avoided, if possible."
179 Avoid wetlands if possible "Wetlands are especially sensitive areas and should be avoided, if possible. Generally, these areas require crossings that prevent unnatural ...
504 Blade only when necessary, avoiding established vegetation Road Maintenance: "Blade only when necessary and avoid blading established grass and forb vegetation in ditches and adjacent to the road."
7917 Bladed material must be returned to original countour "Bladed material must be placed back into the cleared route upon completion of construction and returned back to the original contour before ...
Page:<< Previous|123456789|Next >>   Goto to page: